Bayham
Main Contractor
QOB
Duration
34 Weeks
M&E Consultant
Max Fordham
Project Value
– £800k
Services Provided
Design & Build
Bayham
Main Contractor
QOB
Duration
34 Weeks
M&E Consultant
Max Fordham
Project Value
– £800k
Services Provided
Design & Build
Project Information
A total building refurbishment consisting of reception, basement end of trip facilities and 5 floors of CAT A
New installation works consisted of – service head upgrade and New LV distribution network to all floors.
LV and ELV galvanised cable containment systems, underfloor busbar systems for future office tenants
LED lighting and new Dali lighting control system through out
New fire and security systems