J1011 01

Premier League Studio’s

Main Contractor

Overbury Core

Duration

40 Weeks

M&E Consultant

Hoare Lea

Project Value

– £5.1Million

Services Provided

Design & Build

Premier League Studio’s

Main Contractor

Overbury Core

Duration

40 Weeks

M&E Consultant

Hoare Lea

Project Value

– £5.1Million

Services Provided

Design & Build

Project Information

Completion of a whole floor fit at taking from a Cat A to Cat B. The project involved modifications and additions to lighting control and High level mechanical power. New low level small power and lighting.

A new critical LV distribution system including Switch panels, rising busbar system, UPS’s and generator to support all equipment within the Data centres, Studios and tech rooms. This system also supported the critical cooling system.

Low level power consist of underfloor power tracks to supply to desks via tap lead and power bar modules. Commando sockets for supply to tech desk’s. Also as part of the installation audio visual, Tea points and cleaner’s sockets across the floor.

J1011 02
Large Clean Empty Office Space
Office Meeting Pod

Have a project in mind? get in touch

Speak with our friendly team today about your project, or partnership opportunities

Get in touch